ASHS RELOCATABLE SCHOOL

A temporary relocatable school for Albany Senior High School.

The brief required the design, consent and construction of a school to house 300 students within eight months.
Gareth worked closely with practice director Roy Bloc and was responsible for a large part of the design, developed design and documentation of this project.

The project consisted of 30 modules. 6 x 12 meters, 1 module 3 x 12 meters, 1200 square meters of covered concourse and 500 square meters of gym. 
Work was completed in 2008 and the budget was $5,300,000. 